-DIA 07/11/2022 DADO INÍCIO AO PROJETO DA CIDADE DE PIO XII, EQUIPE TECERIZADA DE SÃO LUÍS, NA SUPERVISÃO DE GLYDSON RIBEIRO.
-
DIA 08/11/2022 06FO 4,060 METROS
-
DIA 09/11/2022 06FO 5,376 METROS
-
DIA 10/11/2022 06FO 6,000 METROS
-
DIA 11/11/2022 06FO 5,547 METROS
-
DIA 12/11/2022 06FO 2,645 METROS
-
CABO 36FO 1,700 TOTAL DE 4,345
-DIA 14/11/2022 O6FO 5,200 METROS
-DIA 15/11/2022 06FO 4,559 METROS
-DIA 16/11/22 12FO 6,000 METROS
-DIA 17/11/22 12FO 6,000 METROS
-DIA 18/11/22 12FO 5,300 METOS
-DIA 18/11/22 06FO 1,530 METROS
TOTAL DE : 53,917 METROS
4.060+5,376+6,000+5,547+4,345+5,200+4,559+6,000+6,000+6,830 = 53,917 METROS.